March 1, 2002

WHAT'S THE BUZZ: ON SALAZAR HALL

----------------------------------------

QUESTIONS OR COMMENTS ABOUT THIS E-MAIL SHOULD BE DIRECTED TO CHRISTOPHER DINNO, christopher.dinno@sonoma.edu

----------------------------------------

March 1, 2002

An article appeared in the STAR last week in which the headline said the renovation of Salazar Hall has been delayed. In fact, that is not the case.


The Salazar Hall renovation is due to be completed by August 1, 2002.
This is still the case.


Salazar Hall is due to be open and be fully functional by the beginning of the Fall 2002 semester.
This is still the case.


There have been a few changes and/or enhancements to Salazar Hall since renovation began. The largest was the installation of an updated air conditioning / chilling system which will require less energy, provide increased indoor air quality, and require less demand on the existing campus chiller system.


A domino effect takes place in Fall 2002 once the renovation is complete:


August: Enrollment and Student Academic Services (ESAS), most Administration & Finance programs, the STAR, the Masters in Computer and Engineering Science Program including 7 labs, the Technology High School, an the various classrooms move into Salazar Hall.


September: demolition of the Village and Administration & Finance Center (temporary buildings) takes place.


October: Construction begins on the student Recreation Center.

 

 