Fall 2005
Student Center task force comes together
Summer 2006
Horberger & Worstell selected as architects
Spring 2008
Designing begins and Sundt Construction is brought on as the Construction Managers
Summer 2008
Alamosa Design comes on as Interior Designer
Spring 2009
Final plans produced, building scheduled at 130,000 square feet
2009-2010
Project put on hold
April 11th - 13th, 2011
Voting on the Student Fee Referendum
November 16th, 2011
Board of Trustees voted unanimously on the Student Center
Fall 2011
Construction begins